Photo : Collected
Preparations are underway for the inauguration of the third terminal of Hazrat Shahjalal International Airport, or Terminal 3 - one of the most exciting and potentially transformative projects undertaken by the Awami League-led governments across three electoral cycles. Prime Minister Sheikh Hasina will inaugurate the first phase of the project on October 7.
However, the full utilisation of the terminal by passengers is expected at the end of 2024. This is due to the necessary calibration and preparation of the equipment used in terminal operations, which is projected to take up most of 2024.
The chairman of the Civil Aviation Authority of Bangladesh (CAAB), Air Vice Marshal Mofidur Rahman,confirmed that Prime Minister Sheikh Hasina will officially open the terminal with the usual fanfare associated with the inauguration of megaprojects under the present dispensation, on October 7.
“The preparation for the inauguration is in its final stages. Structure of the terminal is ready, and now equipment is being installed,” said AVM Mofidur.
He further stated that airlines will be able to use the new parking apron and taxiway . The old terminal's apron can accommodate 29 aircraft, but after the soft opening, the third terminal's apron will be able to accommodate an additional 8 to 10 aircraft.
TDM/SD